|
MINUTES
UTILITIES COMMISSION MEETING
March 18, 2003
Mayor Margo G. Bailey called the meeting to order at 7:30 p.m.
In attendance were Councilmembers Harrison C. Bristoll, Jr., Whaland
Clark, Mabel Mumford-Pautz and James R. Johnson, Medford Capel,
Utilities Manager, W. S. Ingersoll, Town Manager, Jennifer Stead,
Stenographer, and guests.
Mayor Bailey asked if there were any additions or
corrections to the minutes of the previous meeting of February
18, 2003. Mr. Clark moved that the minutes of the previous meeting
be approved as submitted, was seconded by Mr. Bristoll and carried
unanimously.
Mayor Bailey announced that the Utilities Commission
had cash on hand and in banks of $356,207.58.
Mr. Capel stated that three pumps had gone bad,
but were repaired. The flow meter and a fan motor were also worked
on and repaired. A fan motor in a control panel burnt up and was
being repaired.
Mr. Capel stated that he had called three companies
for tank repairs. Two companies had responded with bids. The first
bid would cost $39,000.00 for the 100,000-gallon tank at Foxley
Manor and $132,000.00 for the 1,000,000-gallon standpipe next
to Upper Shore. Mr. Capel said that the second bid from Corrosion
Control was broken up differently, and was more of a maintenance
contract, with repairs and painting of the 1,000,000 gallon tank
inside and out, in 2003; visual inspections from inside the tank
in 2004, 2005, and 2006; in 2007 the standpipe would be washed
and inspected; 2008, 2009, and 2010, visual inspections; 2011
visual inspection with painting of the exterior and interior of
the tanks; 2012 visual inspections. The Contract was similar for
the smaller tank.
Mr. Capel stated that if the Council went with the
second bid, the cost would be $93,970.00 for the first year. Years
2 and 3, would cost $18,000.00 annually. The remaining 7 years
would cost $14,000 annually.
Mr. Capel stated that if new panels were needed
it would cost an additional $36.00 per linear foot.
Mr. Capel recommended that the Council approve Corrosion
Control Corporation’s bid.
Mr. Capel stated that a new tank would cost about
$1.00 per gallon. He said the agreement allowed the Council not
to worry about the tanks for 12 years.
Mr. Ingersoll stated that part of the funding could
come out of this year’s budget. He said that he agreed with
Mr. Capel’s recommendation to use Corrosive Control Corporation,
because in essence they would paint the tanks twice in 10 years.
He also said that other local jurisdictions have used this company.
Mr. Capel stated that Corrosion Control Corporation
could not start the job until June 2003.
Mr. Bristoll moved to approve the contract with
Corrosion Control Corporation for maintenance and painting of
the tanks. The motion was seconded by Mrs. Mumford-Pautz and carried
unanimously.
Mr. Ingersoll stated that in order to keep the BNR
Project going, due to MDE changes, the costs were raised, which
resulted in an additional $5,500.00 in initial design costs (which
were nearly completed) and $82,000.00 for the total design costs.
He asked for the Council’s authorization for the increased
engineering costs.
Mr. Clark moved to approve the additional engineering
costs for the project, was seconded by Mr. Bristoll and carried
unanimously.
There being no further business, Mr. Clark made
a motion to pay the bills. Mr. Bristoll seconded the motion and
it carried unanimously.
Mayor Bailey moved to adjourn the meeting at 7:42
p.m., was seconded by Mr. Clark and carried unanimously.
Submitted by:
Jennifer Stead
Stenographer
Approved by:
Margo G. Bailey
Mayor
|